In plain words
Many small-business loans are partly guaranteed by a government scheme that pays most of the loss if the borrower fails. If the guarantee is part of the loan deal, the finance company counts the expected payment from the scheme when estimating its loss. The guarantee does not make the borrower safer, so a struggling borrower still moves to a riskier stage. The finance company must also follow the scheme's rules, or the claim may be refused.
Why it matters
Much SME lending by finance companies in the region is covered by government-backed guarantee programmes that reimburse a large share of the loss on default, in exchange for a fee. Whether the guarantee is considered integral to the loan decides whether expected recoveries from the guarantor reduce ECL directly or whether the finance company must book the full ECL and recognise any reimbursement separately, under a stricter recognition threshold. The difference can be most of the allowance on a guaranteed book. The scheme's claim conditions, the treatment of fees and the effect of the guarantee on staging all affect reported profit and capital.
Diagnostic questions
Was the guarantee obtained at origination as part of the lending decision, and is it referred to in the loan terms, or was it bought later for a portfolio already on the books? Does the guarantee transfer with the loan if the loan is sold? Who pays the fee: the borrower, passed through by the finance company, or the finance company itself? What percentage of loss is covered, is it calculated on principal only or also on accrued profit, and is it capped per borrower or per portfolio? What conditions must the lender meet to claim (timely notification, enforcement steps, compliance with scheme eligibility rules), and what is the historic rate of rejected claims? Is the guarantor's own credit quality reflected?
Recognition
- Determine whether the guarantee is part of the contractual terms of the loan or is otherwise integral to it, for example because it was required by the lending decision at origination and would transfer with the loan; if so, it is not recognised separately and its expected cash flows are included in measuring ECL.
- If the guarantee is not integral (for example portfolio cover bought after origination that stays with the lender if the loans are sold), measure ECL on the loan without the guarantee and account for the guarantee as a separate right; a reimbursement asset is typically recognised only when recovery is virtually certain, by analogy to IAS 37, unless the contract is itself a derivative measured at FVTPL.
- Assess SICR and staging on the borrower's own default risk; the guarantee reduces loss given default, not the probability of default, and does not prevent a loan moving to Stage 2 or
- 4. Reflect claim conditions: if the lender is unlikely to meet a condition, or a claim is expected to be rejected, exclude the cover for that loan.
- Guarantee fees paid by the finance company for an integral guarantee are a cost of the credit protection; upfront fees directly attributable to originating a specific loan are generally included in the effective interest rate, while periodic fees on the outstanding balance are recognised in profit or loss over the period of cover.
- Fees collected from borrowers and passed to the guarantor are not revenue of the finance company.
- Consider whether a below-market fee charged by a government guarantor is government assistance that needs disclosure.
Measurement
For integral guarantees, ECL is measured using cash flows expected from the borrower, from collateral and from the guarantor, net of the costs of claiming, and adjusted for the probability that the claim is rejected and for the guarantor's own credit risk where relevant. Where the scheme pays a percentage of the outstanding principal or of the loss after recoveries, the model follows the scheme formula. Without discounting, ECL on a defaulted guaranteed loan is the loss before the guarantee less the expected guarantee recovery.
Presentation & disclosure
Disclose: (1) the nature of credit guarantee schemes used and the share of the SME book covered; (2) the policy for deciding whether a guarantee is integral and how guarantees are reflected in ECL; (3) the effect of guarantees on the loss allowance, for example ECL with and without guarantee cover; (4) claims lodged, paid and rejected; (5) guarantee fees paid and how they are recognised; (6) government assistance received, if any.
Common mistakes
- Keeping a guaranteed loan in Stage 1 because the guarantor is the government
- deducting the guarantee from ECL when it is not integral, or ignoring it when it is
- assuming 100% claim success despite a history of rejected claims for late notification
- applying the guarantee percentage to the whole exposure when the scheme covers principal only
- recognising fees collected from borrowers as fee income
- presenting guaranteed and non-guaranteed exposures together in credit risk disclosures without showing the effect of the cover
Simple example
A Dammam finance company lent SAR 2,000,000 to an SME under a government-backed scheme obtained at origination as a condition of the loan, which covers 80% of the loss remaining after the lender's recoveries. The finance company pays the scheme an annual fee of 1% of the outstanding balance. At 31 December the borrower has defaulted (Stage 3). Expected recoveries from the borrower's collateral are SAR 500,000, the lender has met all claim conditions, and the guarantee is considered integral. Discounting is ignored for simplicity and the opening allowance is nil. Loss before guarantee = 2,000,000 - 500,000 = SAR 1,500,000 Expected guarantee recovery = 1,500,000 x 80% = SAR 1,200,000 ECL = 1,500,000 - 1,200,000 = SAR 300,000 Journal entries: Dr Impairment loss on SME financing (P&L) 300,000 Cr Loss allowance - SME financing 300,000 Dr Credit guarantee fee expense (P&L) 20,000 Cr Cash 20,000 (Annual fee: 2,000,000 x 1% = SAR 20,000, recognised over the year of cover. If the guarantee were not integral, ECL would be SAR 1,500,000, and a separate reimbursement asset of up to SAR 1,200,000 would be recognised under the company's policy, commonly only when recovery became virtually certain, by analogy to IAS 37.)
Professional judgment
Whether a credit enhancement is integral is a judgment that IFRS 9 does not define in detail, and practice considers factors such as whether the guarantee was entered into at or near origination, whether it is referred to in the loan terms, whether it was a condition of lending, and whether it would transfer with the loan. Portfolio-level schemes with caps across many loans need careful modelling to allocate the cover. The treatment of periodic guarantee fees (within the effective interest rate or as a separate expense) varies in practice and should be applied consistently. Where the fee is subsidised, the finance company should consider whether IAS 20 applies.
Source basis
IFRS 9 · Financial Instruments
Paragraph references
Verified against the official standard texts used in the IFRS Expert skill.
Related issues
- IFRS 9Classification and measurement of financial assets (SPPI and business model test)
- IFRS 9Expected credit loss staging and significant increase in credit risk (SICR)
- IFRS 9Effective interest rate and amortization of loan fees and costs
- IFRS 9Accounting for modified and restructured loan facilities
- IFRS 9 / IAS 37Financial guarantees and loan commitments: ECL and provisioning
- IFRS 9Write-off and derecognition of uncollectible loans
Educational and navigation content only. Not professional advice. Does not reproduce official IFRS/IAS text. Consult the authoritative standards and qualified professionals; professional judgment may still be required.