In plain words
Steel or cables bought for a project may sit in a site yard for months before installation. Does their cost count toward percentage complete? If the client has not obtained control of them, their cost is left out of costs incurred to date but stays in total estimated cost, since counting it early would overstate progress and revenue. Until installed they are inventory.
Why it matters
Including the cost of steel, cables or precast elements sitting unused in a laydown yard within the cost-to-cost progress calculation inflates percentage complete and pulls forward revenue the customer has not actually received control of yet, since control of the finished, installed work (not the raw material) is what IFRS 15 requires to have transferred, this is one of the most common cost-to-cost manipulation risks in materials-heavy infrastructure contracts.
Diagnostic questions
Have materials purchased or delivered to site or a laydown yard but not yet incorporated into the permanent works been separately identified from installed work-in-progress cost? Has the customer obtained control of those specific uninstalled materials, for example through contractual title and risk-transfer clauses, separately from control of the installed work? Would including the uninstalled material cost in costs incurred to date materially overstate percentage complete relative to work actually performed, and is total estimated cost treated consistently? Is there a reliable materials-on-site ledger reconciled to the progress schedule each reporting period?
Recognition
- Identify materials that have been purchased or delivered to site/laydown yard but not yet incorporated into the permanent works.
- Assess whether the customer has obtained control of those uninstalled materials specifically (which can occur in limited circumstances even before installation, e.g. where the contract gives the customer title and risk on delivery and the materials are specifically identified to the contract), absent that, control has not transferred.
- Where control of the uninstalled materials has not transferred, exclude their cost from costs incurred to date (the numerator) until they are installed, but keep it in total estimated cost (the denominator), because the materials will still be installed and remain part of the total cost of satisfying the performance obligation. Total estimated cost is not reduced, and the measure of progress catches up when installation occurs; removing the materials from both parts of the fraction would overstate progress.
- Only in the narrow case where the customer obtains control of the materials before installation (step 2), the cost of the materials is significant relative to total expected costs, and the entity did not design or manufacture them, may a zero-margin approach be appropriate: recognize revenue equal to the cost of the materials when control transfers, and exclude that cost from both costs incurred and total estimated cost so the margin is earned on the remaining work. This is the only case in which total estimated cost is reduced, and it is a narrow exception, not a default.
- Recognize the uninstalled materials as inventory or a separate contract cost asset until installed, then include their cost in the progress calculation from the period installation occurs.
Measurement
Maintain a separate materials-on-site or materials-in-transit ledger reconciled to the cost-to-cost progress schedule each period so uninstalled quantities are consistently identified, valued, and either excluded from progress or, in the narrow cost-recovery-margin exception, recognized as revenue only to the extent of cost. Reconcile the ledger to physical site records or store records to prevent double counting of materials transferred from store to installation within the same period.
Presentation & disclosure
Disclose: (1) the accounting policy for treating uninstalled materials in the progress measurement method; (2) the amount of uninstalled materials excluded from cost-to-cost progress at the reporting date, if material; (3) any instances where a cost-recovery-margin approach was applied to material procurement, and the rationale; (4) significant judgments applied in determining whether control of specifically identified materials transferred before installation.
Common mistakes
- Including the full purchase cost of bulk materials delivered to a laydown yard in the cost-to-cost numerator as soon as they are paid for, inflating progress well ahead of actual installation
- failing to maintain a reconciled materials-on-site ledger, so double counting occurs when materials move from '
- delivered'
- to '
- installed'
- status
- applying a full-margin (not cost-recovery) revenue recognition to uninstalled materials as if the customer had obtained control of the finished installed work
- removing uninstalled materials from total estimated cost as well as from costs incurred when control has not transferred (for example 17,000,000 / 37,000,000 = 45.9% instead of 42.5%), which overstates progress
- total estimated cost is reduced only where the zero-margin approach applies.
Simple example
A contractor's cost-to-cost calculation at year-end shows SAR 20,000,000 of costs incurred against a total estimated cost of SAR 40,000,000 (50% complete, unadjusted). Of the SAR 20,000,000, SAR 3,000,000 relates to steel reinforcement delivered to the laydown yard but not yet installed, and the customer has not obtained control of these specific materials. Excluding uninstalled materials, adjusted costs incurred = SAR 17,000,000; total estimated cost stays unchanged at SAR 40,000,000, since the materials will still be installed later and remain part of the total cost of the performance obligation. Adjusted percentage complete = 17,000,000 / 40,000,000 = 42.5%. On a SAR 60,000,000 contract, adjusted revenue = 42.5% x 60,000,000 = SAR 25,500,000 (versus SAR 30,000,000 if uninstalled materials were wrongly included). Journal entry reflecting the correct (adjusted) position: Dr Inventory - materials on site (uninstalled) 3,000,000 Dr Cost of construction (P&L, installed portion) 17,000,000 Cr Cash / accounts payable 20,000,000 Dr Contract asset 25,500,000 Cr Revenue from construction contracts 25,500,000
Professional judgment
Whether control of specifically identified materials has genuinely transferred to the customer before installation (permitting a narrow cost-recovery revenue recognition) depends on specific contract terms about title transfer, risk of loss, and whether the materials are uniquely identified to that contract rather than fungible stock, this is a narrow fact pattern that should not be assumed merely because the customer has technically taken title for insurance or security purposes. Distinguishing 'delivered but uninstalled' from 'installed' at a granular level for bulk materials (e.g. partially laid cable runs, partially poured precast yards) requires an operational tracking system robust enough to support the accounting conclusion, and gaps in that tracking are a common source of both error and audit challenge.
Source basis
IFRS 15 · Revenue from Contracts with Customers
Paragraph references
Verified against the official standard texts used in the IFRS Expert skill.
Related issues
- IFRS 15Over-time revenue recognition and progress measurement
- IFRS 15Variations, claims and disputes in contract price
- IFRS 15 / IFRS 9Retentions, advances and contract balances
- IFRS 15Mobilization and contract fulfilment costs
- IFRS 15Significant financing component in contract consideration
- IFRS 15Principal versus agent in subcontracted scope
Educational and navigation content only. Not professional advice. Does not reproduce official IFRS/IAS text. Consult the authoritative standards and qualified professionals; professional judgment may still be required.