Off-plan sales: revenue over time or at handover

IFRS 15 · Revenue from Contracts with Customers

Applies to: Developer (build-to-sell)

In plain words

A developer sells apartments off-plan and collects instalments while building. The question is whether revenue is recognised during construction or at handover. Normally it is recognised over time only if two conditions are both met: the unit has no alternative use to the developer, and the contract and local law give an enforceable right to payment for work done plus a margin, not merely a right to keep instalments already paid. Another, rare route is the buyer controlling the unit while it is built. Collecting instalments progressively is not enough by itself. Otherwise, revenue waits for handover and instalments sit as customer advances, a contract liability.

Why it matters

This is the single highest-stakes judgment for a developer's P&L: concluding over-time versus point-in-time recognition can shift several years of revenue and margin into a completely different reporting period, materially affecting reported profitability, covenant compliance and investor perception. The wrong conclusion (or an undocumented one) is a leading cause of restatement risk in the region's real estate sector.

Diagnostic questions

Is the contract for a specific identified unit that becomes enforceable at signing, or only at a later registration/notarization date? On buyer default, does the contract and local off-plan law entitle the developer to payment for work completed to date plus a reasonable margin, or only to retain instalments as a capped penalty? Can the developer redirect or resell the specific unit to another buyer, or does the unit have no alternative use to the developer? Has a jurisdiction-specific legal opinion been obtained and documented per project, rather than copying a conclusion from another market or group entity?

Recognition

1) Identify the promise: is the developer selling a specific identified unit under a contract that is enforceable once signed (a 'contract' per IFRS 15.9), or is a contract for accounting purposes only formed later (e.g. at a required registration/notarization date)? 2) Test the over-time criteria in order: (a) does the customer simultaneously receive and consume benefits as the developer performs (rarely met for a multi-year built unit); (b) does the developer's performance create or enhance an asset the customer controls as it is created (only if the buyer has recognisable control of the specific unit/work-in-progress under local law before completion); (c) does the asset have no alternative use to the developer AND does the developer have an enforceable right to payment for performance completed to date, including a reasonable profit margin (not just cost or a penalty-capped forfeiture)? 3) Obtain a jurisdiction-specific legal opinion on (i) whether the off-plan contract/escrow law gives the developer a right to full performance-to-date payment (cost + margin) on buyer default, or only a right to retain instalments/impose a capped penalty, and (ii) whether the unit can practically and contractually be redirected to another buyer. 4) If enforceable right to payment (cost+margin) exists AND no alternative use -> recognize revenue over time using an output or input method that faithfully depicts progress; if either condition fails -> recognize revenue at the point in time control transfers (typically legal handover/possession). 5) Document the conclusion per project/contract form (not company-wide) and revisit if the contract wording, escrow law, or market practice changes; get board/audit committee sign-off given the P&L impact.

Measurement

Measurement base: if over-time criteria are met, measure progress using an output method (e.g. surveyed physical completion, units of delivery) or a reliable cost-to-cost input method, excluding from the progress calculation any component (such as land) whose control transferred to the buyer at contract inception under a separate performance obligation. If point-in-time applies, all cash received before control transfer is measured and carried as a contract liability (advances from customers) at the amount received, with no revenue recognized until handover. Subsequent measurement: for over-time contracts, revenue and contract asset/liability positions are remeasured each period as estimated total contract cost and price are updated (recognize the cumulative catch-up); for point-in-time contracts, the contract liability is simply derecognized against revenue at handover, with no interim remeasurement of margin.

Presentation & disclosure

Disclose per unit/project or contract-form population: revenue recognition method applied (point in time vs over time) and the judgment basis; the legal basis relied upon (statute/escrow law and legal opinion) for the enforceable-right-to-payment conclusion; contract liabilities (advances from customers) as a separate line, not netted against contract assets from different contracts; disaggregation of revenue by timing (point in time vs over time) if both populations exist; significant judgments and changes in judgment period-over-period, with quantified impact if the conclusion changed.

Common mistakes

  • Assuming over-time treatment merely because instalments are collected progressively (collection pattern is irrelevant to the control/enforceability test)
  • copying another market'
  • s or group entity'
  • s conclusion without a jurisdiction-specific legal opinion, when escrow/off-plan laws differ materially between KSA, UAE, Egypt and other markets
  • recognizing revenue at contract signing (neither point-in-time control transfer nor a valid over-time measure of progress)
  • treating a capped/limited penalty-on-default clause as if it were a right to full cost-plus-margin payment
  • failing to reassess the conclusion when contract templates or local regulation change mid-project.

Simple example

Scenario: A Riyadh developer sells an off-plan apartment for SAR 1,000,000. Total instalments of SAR 700,000 are collected during a 3-year construction period; the remaining SAR 300,000 is due at handover. Legal analysis under the KSA off-plan sale system concludes that on buyer default the developer may only retain instalments already paid as a capped penalty and cannot claim payment for the cost of work performed plus margin. Because the enforceable-right-to-payment condition fails, the unit is recognized as a point-in-time sale at handover, not over time.
During construction (each instalment received):
Dr Cash 700,000 / Cr Contract liability - advances from customers 700,000
At handover (control transfers; final instalment collected and revenue recognized in full):
Dr Cash 300,000 / Cr Contract liability - advances from customers 300,000
Dr Contract liability - advances from customers 1,000,000 / Cr Revenue 1,000,000
Simultaneously, release the unit's inventory cost (assume total cost SAR 750,000):
Dr Cost of sales 750,000 / Cr Development property inventory 750,000

Professional judgment

The core grey area is whether the enforceable-right-to-payment test is met: this hinges on statute (e.g. off-plan sale/escrow regulations), the specific contract wording, and how courts/regulators in that jurisdiction have historically enforced developer claims on buyer default. Key evidence to gather: a written legal opinion addressing default remedies available to the developer (cost+margin claim vs capped forfeiture), precedent rulings or regulatory guidance, and whether the contract allows the developer to substitute another buyer without the original buyer's consent (alternative-use test). Judgment can differ between projects of the same group where contract templates, land title status, or regulatory licensing differ, so a single company-wide policy is usually inappropriate. Because the conclusion can shift total revenue recognition by multiple years, it warrants documented sign-off and periodic reassessment, especially as off-plan regulation evolves in the region.

Source basis

IFRS 15 · Revenue from Contracts with Customers

Paragraph references

IFRS 15.35IFRS 15.36IFRS 15.37IFRS 15.38

Verified against the official standard texts used in the IFRS Expert skill.