IFRS 15ConditionalReal Estate / Construction

Uninstalled materials in progress measurement

IFRS 15 · Revenue from Contracts with Customers

Applies to: Contractor (build-for-others)

Why it matters

Expensive procured items sitting on site can spike cost-based progress and margin overnight even though the real value-adding work (installation) has not happened; where the customer controls the item on delivery, revenue is capped at cost with zero margin until installation reflects genuine performance. Ignoring this distorts quarter-end and year-end results in equipment-heavy MEP and infrastructure packages, a frequent source of misleading margin spikes.

Diagnostic questions

Have high-value procured items been identified on site that are not yet installed (chillers, elevators, transformers, cladding)? Has control of any uninstalled item transferred to the customer on delivery (title passed, item specifically identified, customer bears risk of loss)? If control has transferred, is revenue on that item capped at cost with no margin until installation reflects genuine performance? Is progress reconciled each period to confirm no margin leakage or double-counting as items move from delivered to installed?

Recognition

1) Identify high-value procured items on site not yet installed (e.g. chillers, elevators, transformers, generators, cladding) and quantify their cost as a percentage of total contract cost. 2) Determine whether the customer has obtained control of the item on delivery to site (e.g. title passes, item is specifically identified/segregated for the contract, customer bears risk of loss), if so, a transfer of control has occurred for that item independent of installation. 3) If control transferred on delivery, recognize revenue for that item limited to its cost incurred (zero margin) at the point of delivery, since including it in cost-to-cost progress at standard margin would overstate performance not yet delivered (the installation service). 4) As installation proceeds, recognize the remaining margin on that item through the normal cost-to-cost progress measure applied to the installation performance obligation (or the relevant part of the single performance obligation). 5) If the customer has NOT obtained control of the uninstalled item (e.g. contractor retains title/risk until installed and commissioned), exclude its cost from the progress numerator and denominator until it is actually incorporated into the works, to avoid overstating progress on work not yet performed. 6) Document which categories of procurement were adjusted and recompute progress each period as items move from 'delivered' to 'installed'.

Measurement

Measure the progress adjustment by segregating procurement-heavy cost pools from installation cost pools in the cost-to-complete model: uninstalled but customer-controlled items are measured at cost with no margin recognized until installation; once installation begins, the item's margin is earned progressively using the same cost-to-cost method applied to the balance of the performance obligation. Where a single performance obligation covers both supply and installation (the typical construction case), the adjustment is a modification to the input method (cost-to-cost) to prevent inputs that do not proportionately depict performance, per the general requirement to adjust an input method for such distortions, it is not a separate performance obligation unless supply and installation are genuinely distinct and separately identifiable. Subsequent measurement: as each uninstalled item is progressively installed, reclassify its cost from the 'delivered, not installed' cost pool into the general cost-to-cost progress base, recognizing incremental margin at that point; reconcile total revenue recognized on delivered-but-uninstalled items to actual costs at each period-end to confirm no margin leakage.

Presentation & disclosure

Explain in the accounting policy/progress-measurement disclosure that the cost-to-cost input method has been adjusted to exclude margin on significant uninstalled materials until installation; quantify, where material, the value of delivered-but-uninstalled items included in contract assets at cost; disclose the judgment used to identify which categories of procurement required the adjustment; disclose any year-end spikes in contract assets attributable to major equipment deliveries, to avoid misleading readers about margin trends.

Common mistakes

  • Taking full contract margin on high-value equipment the moment it lands on site, months before installation, artificially inflating year-end progress and profit
  • leaving customer-controlled delivered items out of revenue entirely (the opposite error), understating recognized progress when control has genuinely transferred
  • failing to identify procurement-heavy milestones at all, so the distortion is never adjusted for in the cost-to-complete model
  • not reconciling the delivered-but-uninstalled cost pool back to actual subsequent installation costs, allowing margin leakage or double-counting when the item is eventually installed
  • applying the adjustment inconsistently across similar contracts or projects, undermining comparability.

Simple example

An MEP subcontractor on a Cairo hospital project (total contract EGP 500,000,000, total estimated cost EGP 420,000,000) receives EGP 90,000,000 of chillers to site in December; title has passed to the customer and the items are specifically identified to the contract, so control has transferred on delivery. Cost incurred to date including the chillers is EGP 210,000,000. Without adjustment, naive cost-to-cost progress would be 210,000,000/420,000,000 = 50%, applying full contract margin to the chillers before installation. Adjusted treatment: revenue on the EGP 90,000,000 chillers is capped at their EGP 90,000,000 cost (zero margin); progress on the remaining performance obligation is measured on the balance of costs, EGP 120,000,000 (210,000,000 - 90,000,000) against remaining total estimated cost excluding the chiller cost, EGP 330,000,000 (420,000,000 - 90,000,000), giving 36.36% progress on the installation-and-balance-of-works scope, generating margin-bearing revenue on top of the at-cost chiller revenue.
Assume total transaction price is EGP 500,000,000 and the margin-bearing portion of estimated cost is EGP 330,000,000 against margin-bearing revenue capacity of EGP 410,000,000 (500,000,000 - 90,000,000 at-cost chiller revenue): cumulative margin-bearing revenue = 36.36% x 410,000,000 = EGP 149,090,909 (rounded).
Journal entries at period end:
Dr Contract asset (unbilled revenue) 149,090,909 / Dr Contract asset - at-cost equipment revenue 90,000,000 / Cr Revenue from construction contracts 239,090,909
Dr Cost of construction contracts 210,000,000 / Cr Contract costs incurred (WIP) 210,000,000
(This avoids recognizing the full EGP 500,000,000 x 50% = EGP 250,000,000 that a naive unadjusted cost-to-cost calculation would have produced, which would have overstated revenue by EGP 10,909,091 and embedded a fake margin spike on the chillers.)

Professional judgment

The core judgment is a control assessment specific to each category of delivered item: has the customer obtained control (e.g. title has passed, the item is specifically identified to the contract and segregated, the customer bears risk of loss or damage, or the contract gives the customer a present right to the item), or does the contractor retain control until installation and commissioning are complete? Evidence includes contract terms on title transfer and risk of loss, insurance arrangements (who insures goods on site), customer sign-off/inspection protocols on delivery, and whether the item is fungible/substitutable versus uniquely specified for this project. A second judgment is materiality: not every delivered item needs this adjustment, it is reserved for items material enough to distort the progress measure (a distortion test), so document the threshold applied and which procurement categories were assessed and adjusted.

Source basis

IFRS 15 · Revenue from Contracts with Customers

Paragraph references

IFRS 15.39–45

Verified against the official standard texts used in the IFRS Expert skill.

IFRS 15 Revenue from Contracts with Customers
Issued: 28 May 2014 · Effective: 1 January 2018

Related issues

Educational and navigation content only. Not professional advice. Does not reproduce official IFRS/IAS text. Consult the authoritative standards and qualified professionals; professional judgment may still be required.